Category: Electrical Projects
Print

Project Summary

Coal Mine - Transportable Mining Substation Upgrade.

 

Substation Upgrade Project
Substation Upgrade Project
Substation Upgrade Project

Project Brief

Upgrade 12 transportable mining substations.

Requirements

  • Install 66kV Circuit Breakers and integrated arc flash protection, including differential protection on 12 transportable mining substations
  • Capital Budget A$7.5 million, over 4 years
  • Project Completion due December 2015

Deliverables

  • New 66kV ABB EDF SK1-1 2500A 72.5KV 25kA Circuit Breaker
  • New 72.5KV 100:1 Outdoor Current Transformer for over current and differential protection
  • New ABB RET615 Transformer Protection Relay with integrated arc flash relay
  • New Fortress Interlocking system

Business Outcomes

  • Project In Progress

Case Studies

Mine Car Park Upgrade

Project Summary Coal Mine - Car Park upgrade.

more info
Major Haul Road Culvert Upgrade

Project Summary Coal Mine - Major Haul Road Culvert Upgrade.

more info
Tailings Dam Construction

Project Summary Metalliferous Mine - Tailings Dam Construction and Filter Wall.

more info
Transportable Mining Substation Upgrade

Project Summary Coal Mine - Transportable Mining Substation Upgrade.

more info
Stockpile Lighting

Project Summary Manganese Mine - Run of mine Stockpile (Cantilever type) Lighting.

more info