Project Summary

Coal Mine - Environmental/Staging Dam.

 

Environmental Dam Project
Environmental Dam Project
Environmental Dam Project

Project Brief

Staging Dam required to pump water 26KM's at 300 Litres per second as part of the mine water management strategy.

Requirements

  • Environment requirements necessitate the need to capture and divert rain water away from the mine pits to a proposed offsite location
  • Mud was dug out and dam was split into two to allow a clean water side to divert rain water and dirty water side to act as a staging dam
  • Budget - A$350k

Deliverables

  • staging Dam constructed to transfer water along mine site
  • Clean water dam with enhanced drainage, capturing all run-off from rehabilitation area

Business Outcomes

  • Staging Dam to allow transfer of mine water
  • Opportunity for future water fill point

Case Studies

Mine Site Water Management

Project Summary Coal Mine - Major Dewatering Strategy; Poly pipe supply and installation.

more info
Replacement of Gantries and Trestles

Project Summary Replacement of 6 Trestles and 2 Gantries on elevated conveyer structures.

more info
New Concrete Tunnel - train load out structural bypass

Project Summary Provide a structural bypass solution to the existing Train load out tunnel.

more info
Mine Water Destruction Processes

Project Summary Coal Mine - Reduction of mine water on site by water destruction processes.

more info
Mine Communications Tower

Mine Communications TowerProject Summary Coal Mine - Communications Tower Improvement Project.

more info