Category: Structural Remediation
Print

Project Summary

Course Coal Product Conveyer - 2 Week Shutdown.

 

Course Coal Conveyer
Course Coal Conveyer
Course Coal Conveyer
Course Coal Conveyer

Project Brief

An existing 40 year old Course Coal conveyer needed to be replaced as the structure, conveyer and centrifuge chutes were beyond repair.

Requirements

  • "like for like" replacement with "modern-day smarts"
  • new conveyer having a screw take-up pulley, Tasman Warajay Head-chute and catch mesh instead of under-pans (no spillage due to enhanced scraper system).
  • Included all project management, tender preparation and assessment, contractor selection process and execution
  • Work to be carried out within a 2 week shutdown period, necessitating extensive structural Pre-Work to be undertaken, adding a high-level of complexity to the overall project
  • Budget - A$4.5 million¬†

Deliverables

  • New Course Coal Conveyer with "modern-day smarts", successfully, delivered within a 2 week shutdown period

Business Outcomes

  • Successful project completion, on budget and on time
  • Zero incidents