Project Summary
Provide a structural bypass solution to the existing Train load out tunnel.
Project Brief
Structural audits had identified integrity issues in the existing Train load out concrete tunnel.
Requirements
- Options study confirmed the best solution was the use of Pre-Cast panels to provide a structural bypass solution to the tunnel
- The new structure was designed as a standalone structure of enough strength to support the coal stockpile independently
- Inclusion of all project management, tender, contractor selection processes and execution
- External structure work commenced during plant operation and the balance of works completed within a 2 week shutdown
- Budget - A$4 million
Deliverables
- New Train load out concrete tunnel structure strong enough to act standalone
- Existing tunnel structure repaired and patched as required to ensure maximum strength
Business Outcomes
- Successful project completion, on budget and on time
- Zero incidents